- BTY line TE-MSC and TE-VSC preparatory work completed. IMPACT/WDP signed on time. Thanks to HSE-RP for update with the groups
- EN-THE intervention planned tomorrow wednesday afternoon fro two quads removal. Transport will take place on Thursday
- Today work in Build. 179 for sorting waste removed from the target area. Thanks to HSE-RP and B. Fost.
- IBRDS planning to be revised according to availability of handling means
- Next week: SCE will cut the side wall to the target area to enlarge the opening (needed for the transfert of dipoles)
Discussion coordination EN-ACE, SCE and SY-EPC regarding B. 197 false floor structure modifications. SY-EPC will try to allocate resources during the summer. Work for the false floor would start at best in September.