Ongoing
- Wisard measurement campaign finished
- IDS measurements campaign ongoing
- ISOLTRAP He-fill tomorrow
- Neutron wall dismantling in SAS at the end of next week
- ISOLTRAP platform (until 18 August.)
- The next phase has started and includes the installation of the staircase and the replacement of the first wooden floor with the new aluminium structure and floor plates.
- A meeting with the cable team, civil engineering and scaffolding contractor to coordinate the different phases of work and related lock-outs of the crane.
- RC6 MR-ToF/ RL7
- Installation continues
- Cabling work in the RC6/RL7 area is expected to be completed this week
- AC cable distribution for the PUMA experiment is still scheduled for week 33/34.
- Meeting for new RAMSES and CHROME RP monitors was held. The RAMSES monitor will go onto the wall next to the RC6 switchyard and mobile solution for the CHROME detector is foreseen for the first years, only to be used when PUMA is actually in the hall (a few weeks per year). Based on the results, it will be evaluated if and where a permanent installation is appropriate
New request
- ISS fill iin the week beginning 21st of September.