Presents: AP. Bernardes, Nina, Stefano
Discussion about the cost of CV for the project IBDRS. The last estimation for the water cooling from Nina indicates 563 kCHF with an additional cost of ~300 kCHF for the air ventilation.
Total ~ 863 kCHF to be confirmed by the sub contractors. => the budget for CV is 690 kCHF.
- Nina indicates the prices increase a lot during the last years
- Nina will place the orders (Egtim and Arceclima) in September - October 2026
- There is no margin on CV water cooling costs but maybe we can simplify the air ventilation ?
- Ana Paula suggests to integrate de air ventilation into the general building 170 ventilation upgrade foreseen in 2027
- Nina will study this solution.
Regards, Stefano