Clock distribution

We agreed to start by defining the required stability at the high-power structure level, and then work together with the RF colleagues to translate this backwards into requirements along the RF/clock chain. The schematics already prepared by Stéphane Curt provide a good starting point.

Tentative timeline: agree on all specifications by the end of 2026, with progressive implementation potentially starting from mid-2027 and completion during YETS 2027/28.

Fast delay units

From an after-meeting discussion with Ben, it appears that this could provide a quick backup solution in case of problems with our present TTL/ECL converter cards, which are currently one of the most critical items as we have no spares.

LLRF klystron drive and signal acquisition / infrastructure

There is currently no concrete deployment plan for this system. Nevertheless, the requirements should be defined by the end of 2026, with first inputs needed ASAP.

Interlock and safety chain

RF signal acquisition chain

Actions