EN-ACE :
- EN-CV platform to be integrated
- Technical room, remove yellow box and optimise Overhead crane control footprint
- Check clash after final 3D integration
EN-THE:
- Some information missing from the supplier and civil engineering, hard stop moved and need investigation
- Optimisation of the volumes and spaces
- Platform + rail: 3D model to be updated
EN-CV:
- Ventilation B.170 consolidation: Decision to be taken in November 2026. Study merging B.170 and B.738 ventilation to be investigated if CONS is confirmed. Pipes in B.738 not impacted in case of change.
- Feed-back from RP on dose rate measurement in the target area “fosse"
- Dump cooling skid to be finalised and integrated
Stefano:
· Feed-back on inspection for the carottage N4, moved to week 41 with RP measurements
· Modify closing of the target area “fosse"
SCE 3D model: Removing column and add bracket
SCE: some update need to be done on the opening of the doors, for emergency reason
EN-ACE: some adjustments around the BORIS tube, Lukas working on it, simulation of the installation done by V.Barozier, SCE should also be involved
EN-CV Pasquale
SCE working on it: Zakaria Bouaicha