Key dates:
  1. Modify metallic structure : 27/02
  2. Reinforce metallic structure : 27/02
  3. Install Monorails + survey : 28/02
Total duration for installation : 2 (3) working days in time window [27/02 ; 28/02]

Action list:
Pascal:
1- Modify Metallic structure to include TIG welding.
2  Request and prepare Fire permit, IS37
3- Supervise & declare RP metalic dust and waste management.
Eric
1- Provide lifting and handling support. 
Tech Coordination
1 Locate the owner of the fiber optics connection box and arrange for temporary removal during welding process.