CMS LS1 WPA meeting for the disconnection & extraction of T1 +/-
→
Europe/Zurich
530/R-030 - BE-EA Conference Room (CERN)
,
action list:
- Eric/Marco -- Check that the T1 cages will be available for re-certification in July. Visual inspection by L dolly should be enough
- Dmitri -- finalize the list of participants in the ACT WP
- Marco --Warm Patrick Lepeule of the need to remove the spider support during T1 removal
- Marco -- Send installation pictures to Eric