CMS LS1 WPA preparation meeting for the installation of the GEM mock up on YE+1

Europe/Zurich
530/R-030 - BE-EA Conference Room (CERN)

530/R-030 - BE-EA Conference Room

CERN

35
Show room on map
Martin Gastal (CERN)
Description
This meeting is designed to assess and review the risks associated with the installation of the GEM mock up on YE+1.
Participants
  • Armando Lanaro
  • David Hay
  • Eric Dugue
  • Gervasio Gomez
  • Maf Alidra
  • Martin Gastal
  • Michel Arnaud
  • Sergei Lusin
  • Stephane Bally
  • Victor Perelygin


The activities to be carried out in the WP will require 1 cherry picker per end
Drainage scheme is being reviewed by P Tropea and will be announced at upcoming TC meetings
The work sequence will start with 3 days of diagnostics of the LV problems encountered on YE+1. The start date for that activity is Thu 04/04.
 
Action:
Victor: Take course to work in SX5 buffer area
Victor: Keep M Gastal/D Hay informed on decision to carry out removal / re-installation of PPanels.
Martin: Check with EE/ES whether the removal / re-installation of PPanels can be done in May.
There are minutes attached to this event. Show them.