Presents: Jerome Pierlot, Bruno Sollier, Andre Augustinus, Stephane Cahuet, Mickael Lonjon, Roberto Divia'

Minutes:
- The scheme of 220V outlets has been presented to EN-EL-BT.
- Lights: 3 zones + trim.
- Offer (SPIE) ready by mid-end August.
- Fancy boxes with 220V & Eth connectors will be added as option.
- Planning (temp):
removal cables: Sep
removal false ceiling and walls, installation false floor: Oct-Dec (interleaved with installation of cable trays)
cabling: Jan
ventilation, false ceiling and lights: Feb

- Next meeting beginning September to validate offers and planning.