Minutes of the 26th WP2 Task Leader Meeting held on 28/03/2014
Present: G. Arduini, O. Brüning, R. De Maria, M. Giovannozzi, P. Fessia, E. Métral, A. Valishev, E. Todesco.
 
Minutes and Follow-up of Actions (Gianluigi)
 
 
Update of the HL-LHC layout and optics – R. De Maria
By assuming the V1.0 layout and the constraint of 3 T for orbit correctors, one would need 2.3 m long orbit correctors close to D2, while keeping orbit correctors for absorbing arc imperfections and shift beam at the crab cavities in Q4. Two other options were studied:
 
The advantage of Option 2) is to reduce length and the number the orbit corrector types in D2-Q4. The drawback is a loss of aperture in D2 TAN of about 1.5 - 1 mm. The advantage of Option 3) is to reduce the integrated lengths of the orbit correctors.
The first option cannot be implemented for space constraints unless relying on a shift of Q4 towards the arc (see later) at the cost of crab cavity voltage or aperture. In order to decide between the two remaining options we need to know:
 
Gianluigi will follow-up these issues with Ezio and Rama. Action: Gianluigi
 
 
Updates from Task Leaders – O. Brüning, M. Giovannozzi, E. Métral, A. Valishev
 
Task 2.2 and 2.3 (Massimo)
A squeeze sequence has been computed by Maxim: it will be finalized by Riccardo to be then discussed with WP3 in view of hysteresis effects.
Miriam progressed with the analysis of the strength requirement for the triplets and D2 correctors. A HSS presentation is planned before Easter.
Tracking studies have been performed by the SLAC colleagues at injection. A reduction of the dynamic aperture by 2 sigmas has been observed, as anticipated by Stephane, as compared to the present nominal LHC optics. A tune scan showed that it could be partially recovered. Stephane mentioned that increasing the tune split would also improve the situation. It should be possible to recover them.
Alternatives scenarios for transferring the losses resulting from Bound Free Pair Production at the IP during ion operation are being considered as an alternative to the installation of 11 T dipoles.
 
Task 2.4 (Elias)
 
 
A task 2.4 meeting has been dedicated to the longitudinal stability issues and the operation of the double harmonic RF system (800 MHz). At present an 800 MHz system is considered for:
 
The mode of operation of the 400 MHz system in full cavity detuning mode will imply a variation of the bunch separation along the bunch train. At present no acceptable solution has been found to adjust the phase of the 800 MHz system along the bunch train accordingly. This will imply a deformation of the bunch profile that will reduce the effectiveness of the above schemes and for that reason investigations should continue to provide an operational scenario for the 800 MHz system compatible with the 400 MHz full cavity detuning mode.
A possible alternative scheme would consist in flattening the bunch profiles with band limited noise although RF noise and IBS will tend to restore Gaussian profiles.
A possible scheme using a 200 MHz Main RF system has been studied too. A 400 MHz RF system would be required as a high harmonic RF system to provide longitudinal stability. Operation in bunch lengthening mode (required to provide flat bunch profiles) would impose a limit on the bunch length to 3.4 ns to avoid loss of Landau damping.
Very likely the 200 MHz system would have to be operated in full cavity detuning mode too. Elias reminded that an ICFA mini-Workshop on “Electromagnetic wake fields and impedances in particle accelerators" will be held in Erice, from April 24th to April 28th.
Task 2.5 (Sasha)
Ji Qiang is conducting strong-strong simulations to benchmark the 2012 observations on bunch shortening. Once this is completed he should be able to start simulations to include the effect of noise of crab cavities.
Work on the possible use of an electron beam as beam-beam long range compensator is ongoing.
 
Task 2.6 (Oliver)
Nothing to report.
 
 
Next meeting will take place exceptionally on Thursday 10th April 2014 at 16:00 to avoid collision with LIU day. The status of the Beam-beam studies will be reviewed.
 
Reported by Gianluigi and Riccardo.