PS/SPS User Meeting
New schedule (v2.3):
Changes affect the T9 beam line schedule:
- The ClicPix run has been extended till tuesday, August 26th.
- The Charm Ionisation Chamber is scheduled 26-28th of August.
- Totem from 28th till September 1rst.
- The INSULAB run is anticipated by 2 days (now Sept 1rst-8th).
- The Beam Lines For Schools get 2 more days to setup the detectors.
4hour technical stop on 28/08 in the morning (Booster RF)
PS Report (Jakub):
Ps is providing beam to EAST, TOF and AD. Problems started on Sunday, with the failure of a vaccum clamp. Part of the accelarator was vented, and the pumping process took us to Monday 11PM before the vaccum interlock was raised. On Tuesday there was a Time recombination system failure on the Booster. Then in the night POPS stoped functioning, this turned out to be due to a cooling interlock, following a wrong manipulation on the East area cooling.
The MD program is RMS current measurement, and not compatible with accesses on the East primary areas. Work on Irrad had to be rescheduled to the afternoon.
T9: Users are Clic-Pix (main), Atlas NSW will stay till 27/08, as Tera Fundation. HVCMOS was informed they have to be out by the time INSULAB starts (Sept 1rst), They start with samples on 14/08, before was telescope commissionning.
T10: CMS RPC finished, they got prologed by a day, to catch up on the problems at the start of the week.