- Actions
- Track patch 1712
for GIN
Now certified. - Track Patches 1537 Mon
box 3.1
Going into production 2 April 2008. - System tests for the registry - including registry
replication and perhaps interworking with the old registry
Written the RPC stuff but not tested yet. - Move registry replication to use multiple resultsets - and document in the spec
- YAIM for mon box should assume that it may have to work with other services on same machine
- Investigate the configuration parameters for MySQL and
for
Tomcat
Tried on RGMA17 but it does not work because the parameters are for the wrong JVM - Add metadata columns to all tables in
consultation with users
This is waiting for patch 1712 (GIN). - Write scripts for sysadmins
showTableOwners and migrateDNForLogicalName are being completed - Update bug 22869
to make it work with old and new code
This requires a new script with more intelligence - Deal with Savannah Bugs - except as indicated more specifically
- Update to GIN - when DB elimination GIN patch has gone out
Address Paventhans bugs including #27808 GIN not handling GlueServiceAssociation properly. Also #22205 and upgrade to Glue schema 1.3 and add ServiceProxy module - Service Proxy Module - add elsewhere.
- Deal with streaming sender which continues to try to send data
- Deal with Savannah Bugs
Only 1 left - Refactor to remove code common to SP and Consumer.
Before work is started on this it should be discussed with Steve to consider the priority. - Track bug 21578 for
adding the UI to the L&B rgma feed.
Zdenek Salvet has said they will try to fix it. Steve has contacted Zdenek who now say he is working on it. - Make system tests work.
Now all three work - on one machine. Will work on basic performance tests and move onto 2 machines!
- Complete spec revision - check the Schema stuff
Will give Ming existing document to write on - Think
about configuration and ACLs
A plan to do this (attached) was discussed. A few changes were suggested - but these were only small changes. The plan will now be elaborated. - Improve R-GMA SAM tests and get into GridView
Now in Savannah at low priority. Assigned person says that it should be out with next sensor release - but no idea when. It has now been postponed - once Antony confirms that instructions are good for the new code will pursue it. - Deal with Savannah Bugs
- Track bug
22605
Glue Service Uniqueid issue. This is in patch
1709
which is now certified.
No visible progress to PPS - Design and implement the python wrapper (without SWIG)
Started - but some problems with Vector of services and the Python communication. SD work will be taken up again when new R-GMA code is out. - Request SAGA SD as ETICS external - C++ and
Python
ANTLR accepted and built. SAGA package being modified to use new namespaces. It now builds OK but need to make changes on the SAGA configuration. Andre is working on it - Get adapter code into ETICS
Checked in - Write two papers when
we know the rules
- Current issues - round table
- AOB
Alastair
Antony
Arun