Options for D2 and Q4 orbit correctors (E. Todesco)

 

Ezio presented an update on the design options for the D2-Q4 correctors. He analysed a case for 4.5 Tm integrated with 105 mm aperture and 194 mm separation. Riccardo reminded (see PLC talk 29/4/2014) that 100 mm and 194 mm separation is an option acceptable for aperture considerations. The main issue is the cross talk between apertures due insufficient iron in between the aperture. 3 T operation would require 75 mm of iron instead of 30 mm available. In this configuration the cross-talk results in dependence of the transfer function between the two aperture current values and poor dynamic aperture. Several options were presented with the field quality degradation resulting from opposite sign of vertical field (the horizontal case is slightly better). Only b3 is quoted but other multipole imperfections are present with about the same order of magnitude:

 

While the transfer function error could be dealt with a two-variable Fidel model, the field quality issue could not be recovered in other ways.

From the discussion it was concluded that the following options should be further investigated:

Action: Ezio.

 

It must be noted that the multipolar field errors integrated over of the set of 4 correctors should remain much smaller than the integrated multipolar field errors of the D2 therefore the field quality of the correctors should be comparable to that of the D2.

 

Massimo asked whether, in the case of a staggered installation of the correctors space could be found for the installation of spool pieces that could be used for the correction of the D2 field errors that are not yet compatible with the requirements. This should be investigated. Action: Ezio.

Ezio asked the operating scenario of the correctors that were given in the following talk.

 

 

HL-LHC V1.1 – Update on optics (R. De Maria)

 

Riccardo presented the impact on the recent hardware integration exercise on the baseline optics as well as the other accumulated changes with respect to HL-LHCV1.0.

The following points were discussed:

 

Riccardo will send an e-mail to all the WP leaders once the optics/layout is available indicating were the optics and corresponding Twiss files are available. This should happen in the coming week. Action: Riccardo.

 

Gianluigi reminded the Task Leaders that the deadline for delivering the deliverable reports is the end of October. The draft reports should be sent to Gianluigi before 15th October and possibly earlier as we will have the Hi-Lumi general meeting in Japan from 17 to 21 November.

 

Ezio mentioned that first estimates of the effect of the fringe field of the triplet quadrupoles have been done and will initially be implemented with integrated multipole kicks and more accurate model as soon as tracking maps will be available.

 

Updates from Task Leaders – M. Giovannozzi, E. Métral, O. Brüning,  

Task 2.2 and 2.3 (Massimo)

 

The tracking campaign is restarted to finalize of the study for:

 

Task 2.4 (Elias)

A new student (C. Tambasco) will work with Tatiana and Elias on the study of the interplay between beam-beam and impedance.

Nicolo Biancacci is starting to work on impedance issues for HL-LHC

The INFN colleagues (M. Zobov and O. Frasciello) are benchmarking GdFidl with CST to further improve the model of the collimators.

 

Task 2.5 (Sasha & Tatiana)

Bad audio prevented Sasha to comment.

 

PLC (Oliver)

Oliver reported that an updated parameter table has been approved by the PLC with a change on the number of bunches and the inclusion of the RF curvature and hour-glass effect in the luminosity estimates.

 

 

Next meeting will take place regularly on Friday 4th July 2014 at 16:00.

 

 