12:00
|
Minutes from previous meeting
()
|
12:05
|
Discuss dimensions of the option 5A enclosures (Tracy)
()
|
12:25
|
Report of review of detector installation and commissioning schedule (Jim Stewart and André)
()
|
12:45
|
Report on ES&H considerations for option 5A (Mike Andrews)
()
|
13:05
|
Report on determining the cost of option 5A (Josh)
()
|
13:25
|
Discuss planning, what can be ready when, for Director’s review and DOE review (Elaine and Tracy)
()
|
13:45
|
Decide whether to proceed on providing specs for option 5A to the A&E firm
()
|