Danica Stojiljkovic
October, 2008
Major work for SEE-GRID; major changes in workplan
----------------------------------------------------------------
- Work on producing contributions for DJRA1.2 -Application-specific Monitoring and Control Tools Design is in progress. Sections requested from CERN are
- 2.1.2 GStat (in 2.1 Main monitoring tools used in SEEGEID)
- 2.2 Other monitoring and control tools, used in EGEE (SAM, GOC DB, GGUS, COD Dashboard, Optional GridView, etc.)
- Testing and reviewing the process of EGEE-SEE and SEE-GRID helpdesk merging. Defining the structure and use cases of merged helpdesk is in process trough correspondence with Alexandru Stanciu and Valentin Vidic
- GOoD shift 06-13/10/2008
Major work for GD-OPS; major changes in workplan
----------------------------------------------------------------
- Administrator of FTS, FTA, FTM and BDII nodes on CERN_PPS site and CERN ROC BDII (update 38 for PPS is applied, predeployment tests performed and report was sent)
- problems with top level bdii appeared on roc-pps instance, tracked in savannah bug 42727 (in progress)
- merging of web tools for tracking PPS and SA3 tasks and from savannah tasks is in progress
- creating tool for registering PPS activities www.cern.ch/pps/ActivityManagement/Registry
- ROC on Duty for three weeks
- 6-10/10/2008 Proactive
- 13-17/10/2008 Proactive
- 20-24/10/2008 Reactive
Major issues arising
--------------------
Major events attended (include links to event/presentation)
---------------------
| 2008 oct 1 |
Introduction to FTS |
Paolo Tedesco |
28-S-029, 10.30 |
FTS-1 slides |
| 2008 oct 10 |
FTS Administration and Troubleshooting |
Paolo Tedesco |
28-S-029, 10.30 |
FTS-2 slides |
| 2008 oct 24 |
CernVM Project |
Predrag Buncic |
28-S-029, 14:30 |
CernVM |
Plans to attend/organize major events (intra-EGEE and others)
-------------------------------------------------------------
Holidays during the period
------------------------------------------------------------
1 day (2008/10/31)