5’ + 5’

A short update will be given about the activities being performed in the 2016-16 YETS by ATLAS and CMS. Particular focus will be given to activities on the critical path, notably the repair of the ATLAS End Cap Toroid Bellows, the cleaning of the CMS magnet cryogenic system and the diagnosis and repair of the water leak in the CMS end-cap.