Julie Coupard,
Katy Foraz
04/02/2009, 08:30
The first shutdown of the LHC machine started on the 17th of November 2008. In addition to typical shut-down interventions and the works already foreseen (e.g. phase 1 collimator installation), some additional consolidation work is needed. On top of this comes the work caused by the 19 September incident and the subsequent tests carried out in November and December. This talk will give an...
Julie Coupard,
Katy Foraz
04/02/2009, 09:05
Alternative options for the current shutdown will be presented. These options include warming up additional sectors to complete the consolidation activities. The potential impact of these revised schedules on the beam schedule in 2009, as well as the length and timing of the following shutdown will also be presented.
Mario Batz
04/02/2009, 09:25
As a complement to the previous talk, a number of questions, that will need to be addressed in order to consider LHC beam operation over the winter 2009-10, will be raised.