Smooth operations + full sites.
Dan has worked through the SLURM/Condor issues and is in the last stages of switching us over to HTCondor-ce on the Harvard side. He's getting help from OSG and coordinating with Jose to get test pilots. There are a couple of snags still, but we should be able to switch over completely later this week. We are similarly in the late stages of doing the same on the BU side.
We have the Mass Open Cloud hardware-as-a-service software working and can successfully build new ATLAS worker nodes in the MOC hardware at MGHPCC. There is a mystery with unexpectedly low network bandwidth between the HaaS worker and GPFS which we're tracking down. After that, we will be testing production jobs and then expanding.
We're getting lined up to purchase an additional 576 TB useable storage, which would exhaust our hardware funds through the end of September.
We've also made progress with BU networking about possible short-term WAN upgrades of NET2 (either 40Gb/s or 4x10Gb/s). The critical issue is actually fees that the University pays to the NoX.