20.03 MONDAY - Stop of Irradiator 9 h, opening of bunker
Start of clean up and detector removal (protection)
21.03 TUESDAY - Opening of the roof (!) and removal of ground plate cosmic trigger
Collection of led bricks
Valve check (4h) for the following mixtures : Ar 70%+ C02 30%, Ar+CO2+CF4, Ar 93%+CO2 7%
22-29.03 Installation of upstream XTDV, opening of the floor
22-24.03 Installation of cosmic trigger chamber
Installation of GEM 2 services and cables
Scaffolding installation
Replace broken neon lights
27-29.03 Irradiator Maintenance
27-29.03 RAMSES monitor relocation
27-30.03 Painting of led bricks
30.03 - DSO Test
31.03 - Move back to the bunker area ? (Maybe 30 before DSO ?)
03-06.04 BLM test campaign (4 days)
07.04 FRIDAY Restart of normal operation
--------------------------
In addition :
- Gas rack to be connected to final power
- Geometer measurement and floor / wall marking of radiation field (day to be defined)
--------------------------
Any other requests :