ERMC and RMM: CAD and Procurement status

Europe/Zurich
927/1-B23 (CERN)

927/1-B23

CERN

35
Show room on map

Action items:

- Order end-plate material (Nico - week 31-32)

- Greg to verify splice tooling once he is back. After verification Loic to decide what is done in 927, what is outsourced (probably all in 927).

- Order aluminium blocks to  produce dummy coils for 77 K assembly (to be decided who and when).

- Order pistons for longitudinal loading (Nico)

- Order all parts required for assembly table (Jeremy)

- Order parts for ground insulation forming (Nico)

- Think on ground insulation lay-out for RMM and way to manufacture it (all)

- Verify list of all parts produced in 927 for winding, reaction and impregnation, what is missing and if something needs to be outsourced (Loic - week 31).

- CGP insulation test with 43 and 44 mm wide Mica (Jacky - week 31). If it doesn't work, re-discussion needed in next step (all).

- Produce drawings with the details in terms of layers of insulation for all manufacturing steps (Jakub)