Coordination: JIRA, Minutes, etc. https://twiki.cern.ch/twiki/bin/viewauth/ProDUNEIT/WebHome
    • 15:00 15:05
      Coordination update 5m
      Speaker: Xavier Espinal Curull (CERN)

      - Next meeting: 8th March at 15:00 room: 31-S-023 

    • 15:05 15:45
      Status reports / round table 40m

      Network deployment

      • (Marc) The Gate for the NP04 experiment was put in place 2 weeks ago (24 January).
      • (Marc) The migration of the NP computing farm from the GPN to the NP02 network has started today (7th February). The network part is successfully done at this moment and the restart of servers should be done soon.
      • (SteveT) Clarification about network network topology: sharing of the 40Gbps in a broken link scenario)

      Data Management

      • (SteveT) Explore pros and cons of having at least the data management part of protodune EOS all at the Meyrin location
      • (SteveT) During the Jan 19 challenge, were there any adverse effects to EOS at the rate we were going?

      DAQ readiness progress

      Speaker: All
    • 15:45 16:00
      AOB 15m