Participants:  Simon Albright, Thomas William Birtwistle, Jean-Baptiste Bonnamy, Louis de Mallac, James Dilwyn Devine, Gian Piero Di Giovanni, Tobias Dobers, Eve Fortescue-Beck, Greta Guidoboni, Klaus Hanke, Jan Hansen, Iñigo Lamas Garcia, Bettina Mikulec, Antony Newborough, Fernando Pedrosa, Gabor Petrika, Serge Pittet, Sylvie Prodon, Andrea Santamaria Garcia, Jocelyn Tan.

Approval of minutes

The minutes of the LIU-PSB WG #200 were approved.

Communications

Report on the LIU Project meeting:

Follow-up of open actions

T.Dobers (2017-08-31) Make a list of starting points of the transfer lines to be sent for approval in an EDMS document.

T. Dobers (2017-09-22) Measure the position of the beam stopper during ITS3.

G. Petrika (2017-08-31) Prepare a document summarizing the ventilation needs for LIU-PSB (EDMS document 1844566).

G. Petrika (2017-09-26) Verify the consolidation required for building 141.

G. Petrika (2017-09-30) Iterate with integration on the installation of the new piping system for cooling.

G. Petrika (2017-09-30) release a new version of the EDMS document 1758628, summarizing the cooling needs for LIU-PSB.

G. Petrika (2017-10-10): circulate an EDMS document regarding the new needs of the POPS-B. New action.

G. Petrika (2017-09-30) Check the viability of the removal of the obsolete heater units during the YETS during TS2.

G. Petrika (2017-12-31): Specify the steps to be taken during the removal of the heaters during the YETS. New action.

L. A. Lopez-Hernandez (2017-09-30) Report about the status of the building 245 modifications.

A. Newborough (2017-09-30) Provide the final price of the recombination dipoles and correctors.

J-M. Lacroix (2017-09-30) Complete integration of PSB-PS transfer line.

B. Riffaud (2017-09-30) Provide proposal for the support of the equipment in the BTP line.

M. Calviani / I. Lamas Garcia (2017-09-26) Prepare the ECR for the PSB scraper/absorber describing both the dismantling of the current equipment and the installation of the new one.

Current Status of the PSB Scraper Study (Iñigo Lamas Garcia)

Comments

AOB

EVM Update (Sylvie Prodon)

Injection Q-strips (Louis de Mallac)

Comments

Tour de table