Participants:  Fanouria Antoniou, Thomas William Birtwistle, Jean-Baptiste Bonnamy, Jan Borburgh, Julie Coupard, Louis De Mallac, Gian Piero Di Giovanni, Jose Antonio Ferreira Somoza, Alessandro Floriduz, Eve Fortescue-Beck, Robert Froeschl, Georgi Minchev Georgiev, Matthias Haase, Christoph Hessler, Jean-Michel Lacroix, Bettina Mikulec, Antony Newborough, Denis Pazem, Gabor Petrika, Serge Pittet, Theo Prins, Andrea Santamaria Garcia, Frank Schmidt, Jocelyn Tan, Wim Weterings.

Approval of minutes

The minutes of the LIU-PSB WG #201 were approved.

Communications

Report on the LIU Project meeting: 5th of October 2017

Follow-up of open actions

M. Buzio (2017-10-02) Provide document describing the specifications of the B-Train system.

J-M. Lacroix (2017-09-30) Complete integration of PSB-PS transfer line.

B. Riffaud (2017-09-30) Provide a proposal for the support of the equipment in the BTP line.

G. Petrika (2017-10-10) Prepare a document summarizing the ventilation needs for LIU-PSB (EDMS document 1844566).

G. Petrika (2017-10-10) Verify the consolidation required for building 141.

New action: K. Hanke (2017-10-24) Find space to store the materials for the finement cavities installation.

G. Petrika (2017-10-10) release a new version of the EDMS document 1758628, summarizing the cooling needs for LIU-PSB.

G. Petrika (2017-10-10): circulate an EDMS document regarding the new needs of the POPS-B.

L. A. Lopez-Hernandez (2017-09-30) Report about the status of the building 245 modifications.

BTP Line Status (Jean-Michel Lacroix)

Comments

New Action: Tobias Dobers (2017-10-24) Change the value of the wide band pick-up in Geode to the one given by the 3D scan.

AOB

Cabling for YETS 17-18 in PSB (Georgi Minchev Georgiev)

New BPM in the BI line (Christoph Hessler)

Comments

ECRs for the coming YETS and LS2 (Julie Coupard)

Tour de table

Next LIU-PSB meeting: 24th of October on the TFB status by A. Blas.