Participants: Fanouria Antoniou, Thomas William Birtwistle, Jean-Baptiste Bonnamy, Helena Botella Esteban, Dario Carloni, Louis De Mallac, James Dilwyn Devine, Gian Piero Di Giovanni, Tobias Dobers, Jose Antonio Ferreira Somoza, Eve Fortescue-Beck, Robert Froeschl, Greta Guidoboni, Matthias Haase, Klaus Hanke, Bettina Mikulec, Antony Newborough, Gabor Petrika, Andrea Santamaria Garcia, Frank Schmidt, Jocelyn Tan.

Approval of minutes

The minutes of the LIU-PSB WG #204 were approved.

Communications

Report on the LIU Project meeting of the 9th of November 2017.

Follow-up of open actions

M. Buzio (2017-11-21): Provide document describing the specifications of the B-Train system.

B. Riffaud (2017-11-30): Provide a proposal for the support of the equipment in the BTP line.

K. Hanke (2017-11-21): find space to store the materials for the Finement cavities installation.

G. Petrika (2017-10-31): iterate with integration on the installation of the new piping system for cooling.

AOB

Update on the heating system removal intervention in the PSB tunnel (Gabor Petrika)

During the last technical stop the risks associated with removing the heating system were identified. These risks are related to dust, water, contamination, and material handling.

Dust

Water

Material handling

A pilot project was proposed to gain experience removing the heating system. It will consist of removing several heating units in the transfer area during the second or third week of the YETS. Two options are proposed using the scaffolding structure:

The first option was chosen as in LS2 there will be better access and machine protection, while only two weeks will be gained with the second option.

Comments

Building 245 – État général travaux génie civil (Helena Botella Esteban)

Modifications derived from the explosion studies

Control room

Basement room

Others

The cost has increased by 20 kCHF due to the explosion studies, the total cost being 310 kCHF. The modifications of building 245 are expected to be completed by February-March 2018, which does not impact the related activities in that building.

Comment

New action Fulvio Boattini (2017-12-05): follow-up of the tip over the issue concerning the installation of the power converters in building 245.

EVM PSB Update (Sylvie Prodon)

4.4 Tour de table

Next LIU-PSB meeting: 5th of December on the B-train measurements (Marco Buzio). Last meeting of the year with Xmas drinks.