Participants: Simon Albright, Maria Elena Angoletta, Fanouria Antoniou, Fernando Baltasar Dos Santos, Wolfgang Bartmann, Aurelio Berjillos Barranco, Thomas William Birtwistle, Louis De Mallac, James Devine, Gian Piero Di Giovanni, Robert Froeschl, Georgi Minchev Georgiev, Matthias Haase, Andrea Santamaria Garcia, Frank Schmidt, Jocelyn Tan, Wim Weterings.

Approval of minutes

The minutes of the LIU-PSB WG #212 meeting were approved.

Communications

Summary of the cost and schedule review (G. P. Di Giovanni)

LN-to-PSB connection project (A. Berjillos Barranco)

The Linac4 to PSB connection will start during LS2 and the work will be divided into:

Activities outside of the access controlled area (starting the 12th of November 2018)

Activities inside of the access controlled area (starting the 7th of January 2019)

Activities in the switchyard area (starting on February 2019)

The Linac4 connection coordination kick-off meeting will take place on the 7th of May 2018, and a second meeting will be done if many modifications are demanded. From June onwards the Linac4 will be included in the PS/PSB/Linac2/3 coordination meeting.

Comments

AOB

Report on the ECRs for LS2 (T. Birtwistle)

Multiple groups

TE-ABT

TE-MSC

TE-EPC

BE-BI

BE-RF

EN-STI

EN-CV

PSB Transmission Line Measurements (F. Schmidt)

Next LIU-PSB meeting: 8th of May 2018 on the EVM report and ECR follow up.