(Jan, after meeting) - Alberto sent PoW slides that contain planning info - these have been agreed with Luca.
EOS detailed plan (with dates)
- May 2018
- New deployment preparation
- Batch tests (new FUSE)
- New MGM stress tests
- EOSHOME00 up
- June 2018
- EOSHOME01 up
- Migration tool to move users from EOSUSER to EOSHOME)
- Move of IT-ST accounts (EOSUSER aka CERNBox)
- July - September 2018
- Move of IT accounts
- New accounts are created on EOSHOME
- Before end of 2018
- Transparent move of larger groups
- Finalise the move
- e.g. Critical account that might have an impact on LHC data taking
FuseX detailed deployment plan
- May 2018
- FuseX deployed under /eos/scratch on lxplus + lxbatch
- Validations and tests form ST, CM, CF, CDA and several other IT power users
- June 2018
- Scale test on /eos/scratch: minimum support for 2000 simultaneous clients
- July -August 2018
- Enable FuseX on EOSHOMExx and on EOSLHCB.
- FuseX will become the default access software for migrated eos users and for everything under /eos/lhcb
- September - End of 2018
- Following the LHCB validation, transparent move of all other instances