Copper cables:

- ITS to decide which power cable to use

- ALICE TC to organise meeting with Ton/Michel to define PP0 removal sequence and dates

- EN-EA underlines that the routing of the cables in CR5 and CR4 has still to be studied

- EN-EA proposes to re-locate PP0 inside the Miniframe in order to save installation time. To be further discussed

- EN-EA suggests to test 4mm2 cables before ruling out this option

- EN-EA to fabricate PP0 and PPA, ALICE TC to provide geometric constraints/envelope

- ITS to split lines with multiple rack destinations in the Excel file (one line per rack or group of racks)

- ITS to indicate cable diameter in Excel

 

Optical fibers:

- Giuseppe has presented the number of patch cords and their length, ITS to cross-check this information (incl. spares)

- EN-EL to provide quotes for both options A and B within 2-3 weeks

- Giuseppe to propose convention for labelling of the trunk cables

 

Cooling:

- Elisa presented the strategy and plans for the installation of the new cooling lines for both ITS and MFT