Collar Instrumentation
We are shooting for the week October 22nd to 26 th
SG are 1.5 mm
8 collars to be instrumented, 4 SG per collar => 32 SG
Ricardo will be the CEA technician working on the SG
Michael believes that this doable in 1 full week. Tech should be at CERN ready to work at 11 at the latest
Coil measuring press
instrumentation will be performed by Michael's team because very thin wires are used.
3 to 4 weeks are required to instrument and calibrate the different parts. (step 1 test with Fuji under press in 927, step 2 instrum, step 3: calibration in mech lab)
Parts should be available from manufacturer at the latest at the end of October to be ready for measurement early december
Strong contrainst 10/12 as the mechanical lab should be empty
Action item:
- Damien/Helene to update the instrumentation plan:
=>next meeting on 03/10/2018, CEA prepares a summary of the instrumentation