Action items:
- CERN:
- CEA:
Update on the tooling for coil rigidity measurement
- measuring bars should be ready to go to 927 on week 48 (nov 26-30)
-set-up of the press should start on week 49/50
- the bottom part of the tool has been sent by DMP to CERN on Nov 19th
Preparation of the SG measurement
- the modules MX 1615 will be used
-CERN will provie the cables fot the connextion to the DAQ during collaring. A 2x20 to 40 pin connector adaptor has to be made on CERN side
- the pin set up of the MW1615 connectros are different from the MX 840.
- twisted pairs should be used: 2/5 should be twisted as well as 3/4. 6 can be twisted with a 6 from another bridge