GIF++ installation and schedule meeting

Europe/Zurich
864/1-B04 (CERN)

864/1-B04

CERN

40
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation & plans for this week 10m

      Yesterday summary : 

      Upstream :

      =========
      ATLAS-MM : left until January, in preparation area for the moment (RP checked)
      CMS-CSC: small chamber hosted on LHCb setup at 3.5m
      ALICE TPC at 2 m unshadowed
      EP-DT2 : 5m next to CMS-RPC
      CMS-RPC : Trolley 1 at 5m, Trolley 3 at 4m
      ATLAS-sTGC : 3.5m

      Downstream :
      ==========
      CMS-GEM 1+2 : 1m
      EP-DT1 : 1.5 m
      ATLAS-RPC : 2.5 m  (back in bunker)  + second trolley to be moved in soon
      CMS-CSC 1 : 2.5 m
      CMS-CSC 3 + LHCb : 5 m
      CMS-DT : 

      Filter scan :
      =========

      Upstream :

      ALICE : full field for 1h  around 10.30am
      CMS-RPC & ED-DT2: first 10000-1000-100 for 1h, then 6.9 for  2h starting 12h

      Downstream :

      CMS-DT:  12h filter scan for ≈ 1 h  460 until 22.

      ============================================

      Access 1h today at 17h
      Access tomorrow 17h for 1h
      Access Monday  9h for 1h

      =========================================================================

       

       

       

       

       




       

    • 09:25 09:40
      Mass Production Test Schedule 15m

      Upstream field :

      ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                                SM1 &  SM2  out until Jan.
                                starting from January 4 chambers per months  - 2 / 4 chambers at the same time  ≈ for 1 year.

      ALICE TPC : 6 chambers, (3 big, 3 small)  - 2 at the same time, swap takes 45 minutes.
                      moving to test 2 big chambers in parallel
                     test restarted (unshadowed)
                     Total 20-30 (aiming for 6 per week,  1 day flushing, few hours for testing)  - 5 weeks

      Downstream :

      CMS-DT  1/15 campaign until January.

      ATLAS - sTGC :  5-6 chambers should arrive beginning of mid January - half an hour for each chamber
                (might be better compatible with upstream)
                In addition : 1 chamber currently flushed in the preparation area, to be moved into the upstream area next week. (to be confirmed on Monday)
                              
       
      ATLAS-RPC : two gas gap chamber arrived, to stay for January.
    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ALICE - FE Electronic upgrade. To be defined.

      Eco-Gas chambers to be tested with new mixture for RPCs.
      - Starting from Mid-January with first chamber. 
      - New gas rack to be installed tomorrow in the gas area

    • 09:50 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      CERN wide power cut on 19.12 - 6h.

      New transformer substation test BE2.  In the morning, lasting 1h.
      Small, but non zero risk (1-2%) of a complete power-cut of max 2 minutes (operator on site).
      https://impact.cern.ch/impact/secure/?place=editActivity:123425

       

      Update / Restart of the BE/CO infrastructure. 21-23.01

       

       

      Ongoing Projects :

      NEW retrieval of TIMBER values : Work in progress, but already available in beta version
      https://epdtdi-pytimber.web.cern.ch/app/gifpp (also linked from main GIF page.

      Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • Requirements during LS2 + Christmas 5m

        CMS-DT : Ar/CO2        70 l/h
        CMS-CSC : AR/CO2     10 l/h
        EP-DT : will let us know

        We potentially need a piquet from the user side. Access to be requested via TC.

         

        Proposal : Stop of gas (except flushing) on Thursday 20.12 afternoon. -> User operation stopped before lunch time.
                         Restart of gas supply : Monday 7.01 -> User operation starting Tuesday

    • 10:00 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)

        Special IMPACT needed for Christmas Closure.

      • New Announcements 5m
      • AOB 5m

        AIDA Transnational Access - Still fund available. Please provide  feedback by tonight to M. Moll.

        Next weeks meeting : different room !   (864-1-B04)