Upstream field :

ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                          SM1 &  SM2  out until Jan.
                          starting from January 4 chambers per months  - 2 / 4 chambers at the same time  ≈ for 1 year.

ALICE TPC : 6 chambers, (3 big, 3 small)  - 2 at the same time, swap takes 45 minutes.
                moving to test 2 big chambers in parallel
               test restarted (unshadowed)
               Total 20-30 (aiming for 6 per week,  1 day flushing, few hours for testing)  - 5 weeks

Downstream :

CMS-DT  1/15 campaign until January.

ATLAS - sTGC :  5-6 chambers should arrive beginning of mid January - half an hour for each chamber
          (might be better compatible with upstream)
          In addition : 1 chamber currently flushed in the preparation area, to be moved into the upstream area next week. (to be confirmed on Monday)
                        
 
ATLAS-RPC : two gas gap chamber arrived, to stay for January.