Weekly summary and plan for the next week :

ALICE arrived with 8 chambers, 2 in irradiation, 6 in corridor.
Friday, Saturday, Monday  :   8h30 Measurement with att. 1 then 1h access (9h30-10h30)
Tuesday : 8h30-9h30 att.1 for 1h, otherwise 2.2 in upstream field
Will continue until Mid-February (one week gap, with no chambers)

sTGC with one test chamber - 1 month test, running
 - Upstream chamber QL1 taken out to preparation area
    2 chambers QS1 QS3 production chamber in upstream position
    (next Wednesday 2 x QS2 will come instead)

CMS-RPC : installation of electronics for EcoGas, installation of chambers will happen next Wednesday.
Currently using the default gas mixture.


CMS-RPC trolly 1&3


EP-DT2  & CMS-RPC :

       for the next days - repeatedly : 2h measurement with att. 100, then 2h no measurement (until 21h)
        will continue with different att factors for the next 2 weeks.

LHCb + CMS-CSC small prototype

ATLAS-MM :   LM2  out   - comes back next year Jan/Feb.
                          Starting from 23 January  (latest 30.1),  2 chambers returning. In upstream area  U1
                          5 filters 50->1 (= one morning).

CMS-GEM 1&2


EP-DT1
CMS-CSC


ATLAS-RPC - 2 setups, IMPACT missing   -
next 6 weeks :  Wednesday 3 short accesses with after Source ON within 3h - after access day.


CMS-DT MB 1&2 - to stop on 30.01 with 1/15 irradiation.
 

CMS-CSC + LHCb  (IMPACT for LHCb missing)

Pb blocks stored on the outside.