Weekly summary and plan for the next week :
------------------------
ALICE : 2 chamber to test, Friday morning. 8h30 - 1h test + short access + 1h + short access
Next week 4 small chambers expected.
ATLAS-MM : 1 chamber SM1 (module6), access during Friday (shadow of ALICE)
test starting on Monday : Scan 2h each day of week (22 to 4.6), starting 9h
GC test successful, will reuse it end of next week.
Training with Beatrice pending.
EP-DT2 : Starting Friday : afternoon 3h scan (filter 100 stable)
+ whole next week starting on 14h
Otherwise : 4.6 filter for most of the week.
EcoGas - last chamber installed, staying on CMS-RPC gas mixture.
CMS-RPC : Scan this afternoon 6.9 - 2h starting at 13h
Upcoming - 1 week test for FE electronics with priority for the access / bunker
Cosmic run with Scintillator / filter 2.2. or 6.9 - to be defined. Around ≈ 20. March.
New chambers arriving 20-25.03 - IMPACT to be done
sTGC Production : return Mid-March
sTGC : 3h source scan after CMS-RPC (≈15h)
One hour access / together with ALICE on Monday.
Access for Friday around 9h for 1h
CMS-GEM 1&2 : Happy
EP-DT1 : need some access (30 min) after the meeting to check some issue with Ar supply
ATLAS-RPC : No special request for this week.
CMS-DT MB 1&2 : No comment.
LHCb : preparation to exchange chamber. Installing it next Wednesday.
CMS-CSC: Continuing radiation.
Enjoing the stable conditions from EP-DT2.