Weekly summary and plan for the next week :

 ------------------------

ALICE :  2 chambers tested last week;                                                                                                                                                                2 chambers to be tested on Monday 11th when ATL-MM is done. The planning is the following: Monday 11/03 access                    around 9am. ATL-MM will remove the chamber and after that, Alice will start the test from 9:30am to 10.30am                                followed by a short access needed to remove both ALICE chambers.                                                                                                Next week on WED 13/03  other 4 small chambers expected. These last batch will conclude the ALICE test                                    campaign. 

ATLAS-MM : still continuing to test 1 chamber SM1 (module6), installed last week, till Monday 11/03 morning
                        Today filter scan started before the meeting for 3 hours and will continue tomorrow morning as well                          (from 9am) for 2-3 hours. During the filter scan period the configuration will be 22  to 4.6.                                      Next week on WED 13/03 another chamber will arrive and will be installed inside the bunker (SM2                           - module 7).                                   

EP-DT2  : 3hours in the afternoon (2pm to 5pm) for next week (filter from 22 to 10)
                 

Otherwise : 4.6 filter for most of the week.

 

EcoGas  - last chamber installed, staying on CMS-RPC gas mixture.
                    

CMS-RPC :  Scan this afternoon 6.9  - 3h starting at 3pm after CMS-CSC source OFF (starting after ATL-MM                              source scan). In case 

                     Upcoming - 1 week test for FE electronics with priority for the access / bunker
                     Cosmic run with Scintillator / filter 2.2. or 6.9 - to be defined. Around ≈ 20. March.
                     New chambers arriving 20-25.03  - IMPACT to be done

sTGC Production :  return Mid-March

sTGC : QL1 test is over. Chamber removed from the bunker yesterday 06/03. QS2 installed yesterday 06/03                        1h test this afternoon with attenuation 1 after ATL-MM is done (it shoud start at 1pm).                                              5h source scan (filter from 600 to 1) on Monday at 11am (after ATL-MM and ALICE are over with both                  tests and access).
            

CMS-GEM 1&2 : Happy

EP-DT1: No comment

ATLAS-RPC  : No special request for this week.

CMS-DT MB 1&2  :   No comment.

LHCb : preparation to exchange chamber.  Installing it next Wednesday.

CMS-CSC: Continuing radiation. Source OFF measurements today for 3 hours (after ATL-MM and ATL sTGC                          are done)