Weekly summary and plan for the next week :

 ------------------------

ALICE :   This week 4 small chambers + 2 big ones. Campaign comes to and end.
                   1 week break,
and 1 slot for 2-3 more chambers (Monday ?)

Friday morning 8h30-12h (with access during last hour)
Saturday morning 8h30-11h (including access)
Monday morning 8h30-11h  (including access)

ATLAS-MM :  Currently no new chamber available.  (SM2 - module 7 not ready for GIF)
                         We will see for next week.

sTGC Production :  return Mid-March. Chamber arrives at CERN on 18.3, to be installed same or next week.
                                Short HV test needed, filter 1 would be required.

sTGC : QS2  (electronics) + QS3 (HV test) installed.  1h test this afternoon with attenuation 1 after ALICE is done. 5h source scan (filter from 600 to 1) on Monday at 11am  -  TO BE CONFIRMED

EP-DT2  :  3hours in the afternoon (2pm to 5pm) for today and tomorrow (filter 10).
                   Stop for next week.

CMS-RPC :  Yesterday installation of Scintillator.  Test of rate during next days. Several 30 minute access.
                     New chambers arriving 20-25.03  - IMPACT to be done
                     Problem with Freon (issue on manometer) 

EcoGas  - last chamber installed, staying on CMS-RPC gas mixture.
           

Otherwise : 2.2 filter for most of the week.


CMS-GEM 1&2 : Happy

EP-DT1: No special request this week

ATLAS-RPC  : Yesterday installation on HV cables.
                          Next week 2 chambers to be installed - new trolley.
                         (presentation expected next week)

CMS-DT MB 1&2  :   No comment.

LHCb : preparation to exchange chamber.  Installing it next Wednesday.

CMS-CSC:  Continuing radiation.
                    Joining Access on Friday and Monday
                    Need stable conditions tomorrow afternoon.