GTT kick-off
Monday 15 April 2019 -
08:00
Monday 15 April 2019
09:30
LBNF – S229
LBNF – S229
09:30 - 11:00
Room: 33/S-004
-Wrap-up discussion of Engineering phase (GTT & CERN) -Presentation of installation procedure (GTT)
11:00
SBND – S233
SBND – S233
11:00 - 12:30
Room: 33/S-004
-KoM -Presentation of Engineering phase (GTT) -Input data list filling (GTT with CERN support) -Procurement activities (GTT)
12:30
Lunch - Glassbox
Lunch - Glassbox
12:30 - 14:00
Room: Restaurant 1
14:00
Dark side project
Dark side project
14:00 - 15:00
Room: 33/S-004
Next steps (CERN) -What is expected by GTT?
15:00
ProtoDune – S140
ProtoDune – S140
15:00 - 16:30
Room: 33/S-004
-Feedback on drilling already performed (CERN) -Final schedule for Temporary door closing (CERN)