GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 → 09:35
      Review of last week operation & plans for this week 20m

      Weekly summary and plan for the next week :

       ------------------------

      ALICE :   2 small chambers tested last week.                                                                                                                                                     3 big chambers arrived.

      ATLAS-MM :  SM1-M3 installed in bunker at 2.9m upstream. 4 week irradiation planned.  (until early May)
                               Universal trolley to arrive end of April. Tentative to be placed in current CMS-DT location.
                               Huge trolley currently modified. Will come back probably 24.4 (if not next week).

                               Otherwise stable conditions at 2.2 (requested by CMS-RPC)

                               Space in front reserved for LM1 - will come in ≈ 2 weeks.
                               Empty trolley to be tested next Wednesday if installation is possible.

      sTGC :   Reception test,  connectors need to be connected,  2 QS2 are inside, go outside today
                     1 QS2 to go inside, maybe one QS1

      CMS-RPC :

      EP-DT2  :

      CMS-RPC :  One trolleys for longevity test and the other for testing the electronics in order to launch the mass production.  One  installed, one (cosmic trigger) to be installed in one or two weeks.
       

      Gas flow needs to be checked, as we are on the limit.

      EcoGas  - Setting up the dedicated mixer (DONE).
       

      Problem with GC, does currently not connect to PC

       

      Thursday :  ATLAS -MM  (morning)  4-5h scan, 1h each from 10-1 attenuation
                         ALICE : morning 8.30 - 12.00 - measurements att. 1 + access.
                          CMS-RPC  : Today 6.9 for 2h needed.

      Friday :      ALICE : Friday 8.30 - 10.30     measurement attenuation 1 + access 
                           sTGC : QS1/QS2  10h30 for one hour source off / filter 1 / source off
                           Eco-Gas : Afternoon 2h filter scan 2.2 to 46000 fem minutes each

      Saturday :

      Sunday :

      Monday :  ATLAS -MM  (morning)  4-5h scan, 1h each from 10-1 attenuation
                        EP-DT: (14-17h) 3h  at fixed attenuation factor  22

      Tuesday :   EP-DT: (14-17h) 3h  at fixed attenuation factor  10
                        sTGC : QS1/QS2  9h for one hour source off / filter 1 / source off

      Wednesday:

      Default condition upstream :  2.2 filter for most of the week.

       

      =====================
      CMS-GEM 1&2 :   2 is Happy,  some problem one GEM.

      EP-DT1:  Fine.

      ATLAS-RPC  :   5 gaps from mass production installed. New BIS gap chambers will be here after Easter.

      CMS-DT MB 1&2 :  Test on the mono-tubes still on going. Preparing for the de-cabling of both chambers expected starting next week. Removal planned 8th of May.

      LHCb : preparation to exchange chamber.  Installing it next Wednesday (not done).

      CMS-CSC:  Continuing radiation and recovering the setups from the preparation area.

      EP-DT :

             
    • 09:35 → 09:40
      Mass Production Tests & Long Term Campaigns - General Items 5m

      General planning for long term campaigns.

    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

    • 09:50 → 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • LS2 restrictions & interventions 5m
      • Bunker Extension Project 10m

        News about the ongoing bunker extension

        Bunker extension :

        ==============

        Bunker layout frozen, work started already.

        Currently estimated start : Early July

    • 10:00 → 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • New Announcements 5m

        Next Wednesday - move of RAMSES to CROME.
        Will need access starting 8h.  We will need SOURCE ON during the day. Maybe several times.

        DSO test in the afternoon.

      • AOB 5m

        Issue with ligth.  Button near access door should enable the light for additional 2h.
        We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLE

        Locked door on Saleve side.
        Proposal top remove the cylinder to avoid the guard locking the door during night times.  -> Cylinder HAS BEEN REMOVED