DQW Crab Cavities Production - Manufacturing Review
Thursday 18 July 2019 -
08:30
Monday 15 July 2019
Tuesday 16 July 2019
Wednesday 17 July 2019
Thursday 18 July 2019
08:30
General Overview of the contract
General Overview of the contract
08:30 - 08:40
08:40
Adequateness and validity of the certification
Adequateness and validity of the certification
08:40 - 08:45
08:45
Completeness of the manufacturing inspection plan
Completeness of the manufacturing inspection plan
08:45 - 09:15
09:15
Review of Manufacturing and testing procedures
Review of Manufacturing and testing procedures
09:15 - 10:30
10:30
Coffe break
Coffe break
10:30 - 10:50
10:50
Implementation of HL-LHC documentation management system
Implementation of HL-LHC documentation management system
10:50 - 11:45
11:45
Open discussion
Open discussion
11:45 - 12:30
12:30
Lunch Break
Lunch Break
12:30 - 13:30
13:30
Check spaces and site organization for: manufacturing, storing of components, storing of finished products
Check spaces and site organization for: manufacturing, storing of components, storing of finished products
13:30 - 15:45
15:45
Draft report prepation
Draft report prepation
15:45 - 17:30
17:30
Presentation preliminary report
Presentation preliminary report
17:30 - 18:00