Minutes

Special MPP-SMP v2 Meeting

The meeting took place on Friday, June 21st, 2019, at CERN.

Participants: V. Kain, L. Jensen, J. Uythoven, I. Romera Ramirez, M. Zerlauth, B. Todd, C. Martin, T. Levens, G. Kruk, J.-C. Garnier, K. Li, A. Apollonio, F.M. Velotti, B. Mikulec, N. Magnin, F. Tecker, D. Nisbet, M. Solfaroli Camillocci, R. Secondo.

The slides of all presentations can be found on Indico.

Overview of the Present System (I. Romera Ramirez)

Ivan presented the layout of the present system, its evolution since the first deployment, the general dependability of the SMP and the motivation to upgrade it.

Discussion

ACTION (MPE-MI): Check how the cross-checker verifies the validity of GMT distributed frames.

Feedback from LHC Operation (M. Solfaroli Camillocci)

Matteo gave general feedback on the SMP from the LHC operators, addressing each of the parameters broadcasted by the SMP system for the LHC machine.

Discussion

ACTION (MPE-MI, BE-BI, BE-OP): Define a strategy for the LHC maximum bunch intensity. Try to implement a common solution to both SPS and LHC.

Feedback from SPS Operation (V. Kain)

Verena gave general feedback on the SMP system from the SPS operation point of view, commenting on new possible requirements and needs for an upgrade.

Discussion

ACTION (V. Kain): Check if there was in fact any availability issue in the SPS in the past.

ACTION (MPE-MI): SHIP destination flag or NA destination flag are not energy related. Check possibilities on how this destination should be transmitted (Timing to BIS or Timing to SMP to BIS).

ACTION (MPE-MI, BE-OP, BE-BI): Clarify the needs of max, mean, average bunch intensity.

BI Connections to SMP (L. Jensen)

Lars briefly introduced the present structure of the BI sources and their connections to the SMP.

Discussion

ACTION (BE-BI, MPE-MI, BE-OP): Do we need redundant BA4 intensity for Probe Beam Flag calculation?

LS3 Plans for Timing and Beyond (G. Kruk)

G. Kruk presented the system plans for LS3 and the considerations on the implementation of White Rabbit (WR).

ACTION (BE-BI, MPE-MI, BE-OP): Beam Intensity and Machine Energy can also be distributed over GMT directly and not over the SMP. To be followed up in the coming weeks.

ACTION (BE-CO): Keep MPE-MI updated on the planning decisions related to White Rabbit deployment.

SMP v2 Hardware Implementation and Timeline (R. Secondo)

Raffaello introduced the general hardware requirements for the SMP v2, in particular in terms of synergy with the BIS v2 project.

Follow-up