Notes from meeting

Participants : Herve allain, David Vincent, Nicolas Commaux, Patrick Graffin, Clement Lorin, Damien Simon, Jean Marc Gheller (CEA)

Carlo Petrone, Arnaud Foussat (CERN)

  1. STAARQ test station layout by J.M Gheller

The main features and scope of supply of the magnetic measurement shaft categories for MQ and MQYY to be cold tested on new STAARQ test station were presented.

The CAD layout of the station area for magnet uplifting, rotation, removal of transport corset jig was shown

The access insert preparation platform will use two levels in order to perform splices, to install instrumentation, the AC+MM coils mechanical assembly  and to carry out related connections at the top cryostat level.

The magnet once connected on insert platform shall be moved out through the side of the insert platform once magnet is fully equipped.

As reminded, the design of lambda plate is adaptative to both MM and AC systems size requirements as presented. 

The test cryostat has been designed within the following weight and size limits:

The assembly of the magnet insert resting onto a dummy cryostat flange foresees some possible trial assembly of the lambda plate onto the platform with Fuji pressure sensitive film.

The environment around the cryostat top flange and dimensions was shown to be able to design dedicated AC support jig.

  1. AC procurement SCHEDULE- J.M. Gheller

MQYYM:

MQ, MQYY:

  1. MM shafts design options – C Petrone

Several  existing options for the MM shafts were presented, analysing the pro and cons as function of the technology and budget constraints

 

The first idea of a scanning coil system to reuse LHC shaft of MQ has been discarded due to extra development and hardware cost

The option 1 consists in using one dedicated array of measuring coils in each of two apertures and would require large amount of handling, risky operation.

The option 2 would require 2 arrays of coil in each magnet MQ, MQYY with a total of 4 coils

The last option 3 would require 2 coils of MQ type, extended in length to cover both magnet lenght

or novel collared magnet design

The decision on to the option of design is urgent to be taken to optimise the number of segments either to 5 to 6 and the final shaft dimnnsio.

length, to refine the scope of supply and start procurement form 2020.

  1. Open design items (all):

 

  1. Test station area visit (All):

The test cryostat hall area to be refurbished has been visited. A pit shall be drilled in the zone of the future insert for preparation work.

The possible locations of the MM system working area requirement of minimum 8 m2 , less than 8 m away from cryostat.

The available floor area is located under the main 20 kA busbars routed at 3 m height and the impact from the bus magnetic field should be assessed.

  1. Action items:

A00 -The final option amongst available advanced design of scope of supply of shafts and anticryostats has to be decided by CEA, CERN management as function of budget constraints and available resources.

A01- CEA to design the interface holes in end plates of magnet for the MM shaft centering device.

A02-  As a total of 220 ke budget is needed to develop dedicated measurement ACs, Moles for the MQYY. Action on CERN to clarify the availability of the budget

A03 - A preliminary estimate of the need for the intervention by CERN personnel on CEA site for the preparation and operation start, shall be done by DS.

A04 – The stability of PC current is required and its measurement accuracy on the station shall be confirmed by CEA.

A05 – Drawing approval: The future assembly drawings of the magnetic measuring shafts by CERN shall be validated by STAARQ team

The assembly sequence drawing of shafts into the AC by CEA shall be checked,  validated by CERN.

A06 – A design review of open points abovementionned shall be organised by CEA before launch of hardware procurement.