Notes from the meeting (Massimo)
Vasco Massimo Federico Roberto Mikolaj Latchesar Giulio Andrea Sylvain Costin Ruben Peter Uli Mohamad Taku Niko
- Config of IB in CR1 s/Uli/Roberto/
- FLP control to be installed (1 for VS one for IS)
- Before January weak integration FLP and EPN (2-click start of run)
- In January integration (1-click start of run) (Vasco and Mohammad)
- EPN ready to use the EPN prototype to study stability
- Fairmq/DDS minor glitches (when using FMQ1.4.8+ and DDS3). In hand (Giulio and Mohammad)
- Where do we write notes, howtos...
- PeterH to make a proposal next week
- Discussion on SW installation. Use CVMFS? Different opinions. Not urgent but to be rediscussed
- Control network and network control discussion (Massimo to call a meeting with Uli, Roberto, Johannes and Mikolaj). Clarify the necessary fencing
- Andrea: Disucssion on LTU and MCH FLP
- Their FLP is in the cavern and signals are available in CR1.
- The VS LTU had been installed in the CR1 for the VS tests only
- CRU firmware: hope to converge on a stable version (v5?) otherwise monking around needed between FEE and CRUs
- Roberto: note that CR1 will be shut down on Fri 20th and restarted when CERN reopens