CFU and Bench modification for HL-LHC IT magnets testing in SM18

 

Wednesday, 15 April 2020

https://indico.cern.ch/event/910209/

 

  1. The particularities of the hydraulic and electrical interconnections between the CFB and the cryo-assemblies Q2a, Q2b and Q1/Q3 (being Q1 and Q3 99% identical). Some of the models will be updated. The detailed description is available in:

https://indico.cern.ch/event/910209/contributions/3828903/attachments/2021112/3379414/Quadripoles_HL-LHC_equipement_cryo-assemblages_pour_test_SM18_2020_05_15.pdf

No major comments during discussion, they will be reviewed by Philippe Pierrot and Gabriella Rollando.

 

  1. The configuration of D2 to be tested in bench C 3D model of the “fermeture a vide” which involves all the parts needed to link the cryo-assembly to the CFB and the parts needed to close the MRB side:

https://indico.cern.ch/event/910209/contributions/3828903/attachments/2021112/3379410/D2_HL-LHC_2020_04_16.pdf

 

  1. Relation of parts needed showing availability and status of production for the test for both the cryo-assemblies and the benches which will host the magnets: https://indico.cern.ch/event/910209/contributions/3828903/attachments/2021112/3379400/Fermeture_vide_isolation_HL-LHC_D2_et_Q1-Q3_2020_04_16.pdf

 

 

 

Y. Raqai is in charge of the qualification tests of the current leads cable that will be installed for the 2 kA lead:

  1. High voltage test at room temperature, in a GHe atmosphere of the 2 kA current lead cable insulated and placed in the tube as it should be installed in the CFB.
  2. Powering test of the 2 kA current lead cable in a vacuum atmosphere in the diode cryostat. This required a long development for the safety qualification of the task which is almost ready. The next step is production of several parts needed for the test.