Present: Pierre, Raul, Fabio, Tommi, Alexej
Pierre informed that the two pallets with the parts for cavity frame and the trolley must be removed from the main workshop by Monday.
Alexej will take care of this on Monday with Karol from Main workshop and somebody from B252.
Fabio informed about results of the first tests of the revolver magnet holder. See the slides. Two issues have been mentioned which might have been the reason for no plasma. polarity of the magnets were not correct and the assembly had arcing due to floating potential. This will be corrected in the next tests in 2 week when Alban is back.
Tommi prepared the drawings for some part of the coating system assembly, see his contribution. He expect some feed back from Marco G. concerning fabrication of the parts in order to finalize the drawing.