15/10/2020, 14:00
- ALICE went into production on schedule on Monday 12 October. Well done everyone!
- Michael: Namespace reconciliation (1.8 million files in Alien are not in CTA)
- David: ALICE probe: Alice authentication relies on
xrootd-alicetokenacc
RPM and secret magic sauce from Andreas, see #105 and...
15/10/2020, 14:10
- See Putting EOSCTALHCB into Production (CodiMD)
- Successful 200TB test with 10 tape drives and one buffer server for 2.5GB/s of constant archival throughput. Chris will now recall the files.
TO DO/Schedule
- TPC test from EOS LHCb to T1s
- DAQ test should be possible in November (tentatively 9 Nov 2020)
15/10/2020, 14:20
- See Putting EOSCTACMS into Production: TO DO List
- See Notes from meeting with CMS 02/10/2020
- CMS say write tests are satisfactory
TO DO
- Michael/Giuseppe: clean up namespace, identify any tapes which need to be repacked
- Recall...
15/10/2020, 14:30
- Migration of SMEs from CASTOR to CTA, see Putting EOSCTAPUBLIC into Production
NA62
- NA62 repack is proceeding
- NA62 offline integration: Vova has created the VM with AFS+EOS to allow the tests to proceed
- NA62 migration test onto EOSCTA PPS, see issue #72
- NA62 recall...