Participants: Simon Albright, William Andreazza, Fanouria Antoniou, Thomas William Birtwistle, Gian Piero Di Giovanni, Jose Antonio Ferreira Somoza, Vincenzo Forte, Eve Fortescue-Beck, David Hay, Bettina Mikulec, Antony Newborough, Gabor Petrika, Carlo Petrone, Serge Pittet, Andrea Santamaria Garcia, Jocelyn Tan.

Approval of minutes

The minutes of the LIU-PSB WG #221 meeting were approved.

Communications

LIU Project Team Meeting

LIU Beam Performance Meeting

LIU-PT meetings with dedicated equipment group

TE-VSC activities and status (J. A. Ferreira Somoza)

J. A. Ferreira Somoza summarized the activities of TE-VSC for the LIU-PSB by area:

BI line

BT line

BTM line

BTP line

PSB ring

Budget

Comments

AOB

Update on the ECRs

Multiple groups

Concerning the following topics, B. Riffaud communicated that the design works are in progress and will be sent to the integration team when complete.

TE-ABT

TE-MSC

TE-EPC

BE-BI

BE-RF

EN-STI

EN-CV

EN-ACE

Tour de table

Next LIU-PSB meeting: 9th of October 2018 on the commissioning of the new wire scanner by Jose Luis Sirvent Blasco and an update on the resistance dampers by Frank Schmidt.