Participants: Maria Elena Angoletta, Miroslav Georgiev Atanasov, Giulia Bellodi, Bartosz Przemyslaw Bielawski, Jean-François Comblin, Julie Coupard, James Devine, Gian Piero Di Giovanni, Eve Fortescue-Beck, Georgi Minchev Georgiev, Marine Gourber-Pace, Matthias Haase, Verena Kain, Bettina Mikulec, Gabor Petrika, Fabio Pozzi, Andrea Santamaria Garcia, Frank Schmidt.

Approval of minutes

The minutes of the LIU-PSB WG #224 and LIU-PSB WG #225 were approved.

Communications

General

LIU-PT Meeting

LIU Beam Performance Meeting

LIU-PT meetings with dedicated equipment group

Open Actions

T. Dobers (2018-10-23): Produce the tilt measurement tool and perform measurements on spare / future magnets.

Linac-to-PSB LS2 schedule (J. Coupard)

J. Coupard presented the detailed schedule of the Linac4 connection. She reminded that S. Mataguez is the Activity Technical Coordinator and that she is the Facility Coordinator for the Linac4 connection.

Concerning the documentation, there are two ECRs missing, namely the LBE line and infrastructure upgrade for the Linac4 and the new BLM installation in the transfer lines. For the Work Package Analysis, all the work about the connection is in engineering check. The dedicated procedures, which concerns the equipment to be operated during the beam tests in 2019, are to be validated by everyone involved.

The schedule is divided between the work to be done in Linac4 and the connection interface in Linac2 and Linac4.

Completion of the Linac4 transfer line

Partial dismantling of Linac2

Reconfiguration of the power converters in B363

Connection of the Linac4 to the LT.BHZ20

Reconfiguration of the Beam Emittance Measurement Line (LBE) in the PS SwitchYard

Linac4 beam tests

J. Coupard commented that the schedule is continuous, with little margin. The 3D integration is complete and all documentation and differential drawings are being finalized.

She thanked A. Berjillos for his work as a fellow preparing the Linac4 connection activities.

Comments

AOB

Update on the ECRs (T. Birtwistle)

Multiple groups

TE-ABT

TE-MSC

TE-EPC

BE-BI

EN-STI

EN-CV

EN-ACE