User Reports / Overview :
----------------------------------
ATLAS-MM : Long term chamber to be installed tomorrow (LM2 (Pos,D02)).
Wednesday, 2 new large detectors to installed. (Moving to large detector for the next months)
New detectors are expected every Wednesday. Running from pre-mixed bottle (bank).
Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
Will be clarified in the coming weeks.
ATLAS - sTGC : 5 chamber in preparation area. 2 chamber to be moved in tomorrow.
20 large chambers expected on Wednesday.
CMS-CSC: Setup from preparation area to be moved (bunker upstream or Bld. 904).
EP-DT1: Moving back to position on Friday.
EP-DT2 : Restart tomorrow. New (additional) detector to installed on Wednesday.
Request to have the default value 2.2 in upstream.
CMS-DT: Rails back installed. Electronic racks needed mid-November.
Chamber expected to be installed around February.
EcoGas : Restart Ar flushing as soon as gas is back.
CMS-RPC : Plan to restart on Monday. iRPC will stay for another month.
Trolley 1& 3 in bunker. Cosmic trigger activity to restart also on Monday.
ATLAS-RPC : No report.
LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
---------------------------------------------------------
Stop of Gas supply for 7.01 to 10.01 !
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
introduction, goal of the test, plan, needs
BLM measuring campaign announced / ≈ 100 BLM, 3 days approx. First half of 2020 ?
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)
Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
Improvements needed or planned for the facility.
Ongoing :
=============
PRIMARY & RAW WATER 2/2
• Status
– CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.
– BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
– BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).