LIU-SPS Coordination Meeting
→
Europe/Zurich
865/1-D17 (CERN)
Present:
I. Karpov, F. Follin, A. Rey, L. Jensen, H. Bartosik, G. Papotti, E. Carlier, C. Pasquino, F. Velotti, K. Li, V. Kain, E. Shaposhnikova, A. Butterworth
:
-
Agenda is now accessible from all within CERN
-
Antonio to get in touch with Christos for the SPS BLM ISTs (ACTION)
Agenda:
-
Still to check AllClockDistr which is not in LSA after FESA2 migration - look at this offline with Anthony and Andy (ACTION: Anthony and Andy to have a look at this)
-
FESA classes for FGCs - to be checked; in simulation mode we can have a test; should arrive around 15 February
-
ALPS has already been well tested by Stephane in BA3
-
ALPS interlocks needs to be checked early together with Yannick!
-
- )
-
Ideal to look at FESA class readiness
-
Andy presents cavity control, beam control and beam based measurements
-
As HW will be ready close to the startup, we need to created FESA classes with APIs that can already be used in simulation mode so that OP can start integrating
-
Generic components are well advanced; timings, functions, acquisition
-
By end March RF wants to have all devices defined and instantiated so that they can be instantiated in the CCDB and LSA
-
Cavity control close to completion; next task will be a mock beam control interface and classes
-
Next, check FESA functions
-
Assume cavity control by March (including set-points and loops), beam control by April - we can start building Makerules
-
Need to foresee Functions FESA soon
-
VME crates powering up should be checked - (ACTION); Anthony has made sure that all crates are update with CC7 and all FESA classes have been upgraded to FESA3 --> this migration needs to be tested as well (ACTION - Anthony; go offline through list of legacy hardware to be tested)
-
Clock selection will be checked explicitly during clock selection - OP needs to be able to manage the settings - (ACTION - not to forget to manage this correctly, Guilia to follow up; Kevin to check with Fabio on application)
-
Long blow-up will be in a separate FESA class; for the long. blow-up we will have a similar interface as in the past; one continuous function now as we have more memory
-
FESA class forctionsions should be ready ; acquaition ready soon.
-
Giulia stressed to have one general buffer as well as one separate one for the SPSQC (ACTION - Andy to check if FESA classes need permanently allocated buffers to be able to push to post-mortem)
-
Wolfgang comments that all control for legacy beam observation whether this is covered - Guilia is planing to re-install what was installed.
-
- that need to be completed during commissioning. A checklist of dry runs was put together so that it can be followed up during each meeting; the same was done for the RF integration.
- Round table:
- ATIM generation is almost ready; configuration still be checked
- Verena asked about the layout sequences in the repository - this is noted and still being worked on
- Giulia: was looking at RF integration and commented to also add the OP applications (ACTION - to be checked with Guilia)
- Ivan: algorithm on the making for emittance blow-up; (ACTION: Kevin to get in touch with Ivan for smarter generation)
- Verena; ISTs safety procedures almost ready - still some open questions here; bake-out will be added to the risk assessment; Verena asked whether this additional tasks are included in the planning (Etienne to check with Antonio etc.)
- Fabio - ATIMs application passes directly through LSA - need to check whether setting are good; another meeting for BLMs for inclusion into SIS is scheduled;
- Stephane: BIC injection question was raised once more to have another input; Etienne sais that this is feasible in principle; (ACTION: have an offline discussion)
- Lars: slip stacking - people are worried about the (ACTION: to be checked - get specs for RF revolution frequency in particular during slip stacking; also needed for the beam dump)
- Elena: Theo is working on implementing an algorithm for asymmetric slip-stacking. Elena asked to prepare two cycles that can also deal well with the fallback ions beam without additional plateau (ACTION: foresee for ion preparation).
- AOB:
-
- Access system, IST, fire safety W34-35, overview has been announced, by-pass for the ABT team is negotiated (still to verify with HSE) and OK.
-
- Next meeting - TBC:
- Bruno and Mike for procedures
There are minutes attached to this event.
Show them.