Motor Controller - BI-CEM meeting

Europe/Zurich
774/1-079 (CERN)

774/1-079

CERN

20
Show room on map
There are minutes attached to this event. Show them.
    • 14:15 14:20
      Intro & Objectives 5m
      • Clarify meeting goals: feasibility of SAMBUCA vs. MCOX and next steps
      Speaker: Federico Roncarolo (CERN)
    • 14:20 14:30
      BI Systems Overview 10m

      Based on Recap of BI-PM internal discussion (Aug 28 notes)

      • Class of instruments equipped with motors
      • Present installations & migration needs
      • New systems required for LS3 (quantities)
      • Identification of systems difficult to maintain outside BI (e.g. HIR DBs)
      Speakers: David Belohrad (CERN), Federico Roncarolo (CERN), Stephane Burger (CERN)
    • 14:30 14:45
      Current BI Controllers 15m

      (also from Aug 28 notes)

      • Legacy VME systems
      • MCOI with GEFE
      • MCOX SoM based
      Speakers: David Belohrad (CERN), Stephane Burger (CERN)
    • 14:45 15:00
      MCOX (BI) – Status and Perspectives 15m
      • Prototype status and pending Gateware porting from VFC to SoM (~3 months FTE ?)
      • Expected cost per channel
      • Applicability beyond BI (potential inclusion in CEM portfolio)
      • Risks: long-term Phytron procurement, production/maintenance burden
      Speaker: David Belohrad (CERN)
    • 15:00 15:20
      SAMBUCA (CEM) – Status and Perspectives 20m
      • Prototype status (phase 2, collimators)
        • final LS3 production roadmap - schedule
      • Expected performance for BI use cases (low-power motors, cabling, form factor)
      • Software/firmware support and maintenance responsibilities
      • Expected cost per channel
      • Availability for BI testing
      Speakers: Enrico Bravin (CERN), Dr Mario Di Castro (CERN)
    • 15:20 15:40
      Comparative Review, wrap-up & Discussion - ALL 20m

      (Aim at preparing bullet points for discussion - BI-PM team)

      • Cost, performance, and integration trade-offs
      • SAMBUCA integration to existing systems
      • BSR and AWAKE existing + upgrades - options
      • keep AWAKE legacy , recuperating electronics form HRM, BGC, LAbo which will be moved to new system
      • Operational responsibilities (design, production, exploitation, maintenance)
      • Standardisation vs. diversification of solutions

      Future Ownership & Collaboration Options

      • Scenario: CEM taking over responsibility for MCOX
      • Scenario: CEM contributing to MCOX design completion while BI retains ownership
      • Pros/cons for BI and CEM in both cases (resources, know-how, long-term support)
      Speakers: Daniele Butti, David Belohrad (CERN), Federico Roncarolo (CERN), Dr Mario Di Castro (CERN), Stephane Burger (CERN)