WP06 - RFQ Conditioning
This work-package is responsible for and organises all equipment, procedures and services that are required to condition the RFQ2 namely
- the RF window and wave-guides up to the fixed point
- vacuum equipment on the RFQ
- cooling water distribution from the water jig
- thermal stabilisation and related controls
- LLRF controls
- general controls and interlocks
- RFQ protection and surveillance
- RFQ conditioning and RF operation